WHAT ARE THE PHASES OF WORK?
Phases 1 and 2 will include the demolition of the building behind the faade and the support of the existing faade. At this time, the buildings new superstructure will also be erected (new steel columns and floors). The last stage of the project will be the interior build-out of the project. A phased schedule is available here.