Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

On CPR Format 1, Section 8 (f) Management Reserve, column (15) is shaded. Does this mean that I cannot put management reserve in this cell?

0
10 Posted

On CPR Format 1, Section 8 (f) Management Reserve, column (15) is shaded. Does this mean that I cannot put management reserve in this cell?

0
10

A. Management reserve data should be included in Section 6 (a), (b), and (c) Estimated Cost at Completion under the Management Estimate at Completion (1). As per the DID, the estimate at completion in column (15) would only be for work included in the Performance Measurement Baseline (PMB). Any impacts due to additional risk, management reserve, or higher level management knowledge would be included in Section 6 (1).

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123