On CPR Format 1, Section 8 (f) Management Reserve, column (15) is shaded. Does this mean that I cannot put management reserve in this cell?
A. Management reserve data should be included in Section 6 (a), (b), and (c) Estimated Cost at Completion under the Management Estimate at Completion (1). As per the DID, the estimate at completion in column (15) would only be for work included in the Performance Measurement Baseline (PMB). Any impacts due to additional risk, management reserve, or higher level management knowledge would be included in Section 6 (1).