Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

With regards to financial caps, should Section G apply to Quantified Maintenance items and Provisional Sum items?

0
Posted

With regards to financial caps, should Section G apply to Quantified Maintenance items and Provisional Sum items?

0

A. Yes. The Ministry is reserving the option of asking the Contractor to provide Quantified Maintenance Services up to the $35,000 cap and then asking another contractor to complete the work or completing the work in-house. Alternatively, the Ministry may ask the Contractor to complete all the work as Quantified or as additional work.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123