Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

Will the June 1, 2012 in-service requirement be different for wind resources than it will be for solar photovoltaics?

0
Posted

Will the June 1, 2012 in-service requirement be different for wind resources than it will be for solar photovoltaics?

0

There is no in-service date requirement per se. The June 1, 2012 is the start date for performance under the Long-Term Master Agreement. This date is fixed and applies equally to all resource types. 9/14/2010, in Long-Term Renewable Energy and RECs RFP.