Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

Why wasn’t the track standardised at the same time as the track upgrade?

standardised time track upgrade
0
Posted

Why wasn’t the track standardised at the same time as the track upgrade?

0

A. A standardised track requires changes to the railcar maintenance facilities and conversion to standard gauge railcars. Standardisation therefore needs to be staged across the entire metropolitan rail network. The Belair line renewal used gauge convertible sleepers to allow for future conversion to standard gauge.