Why does CTM fulfill a demand using the transportation lane with the lowest priority ?
If the demand is fulfilled late and you use Keep Lateness to a Minimum procedure (BackwardProjection5), CTM planning selects the source of supply as early as possible and it only considers priorities, costs and quota arrangements when there are several sources of supply with the same availability date.