Why are three sets of plans submitted for the permit application package?
Permit application drawings are submitted as “Issued for Construction”. Following final review and approval, each set, as well as the permit application, is provided with signature approval by a Professional Engineer within the Town’s Engineering Division. One set is returned to the Contractor, to be retained onsite during the project implementation period. The second set is filed with the Engineering Division. The third set is held and used by the Town’s Engineering Inspectors for use during site inspections.