Why are renovations needed in the Rainbow Room (Art Annex)?
The Rainbow Room/Art Annex, located outside of the main entrance of the secondary campus, currently serves as an additional art room. To continue using this facility, it must be connected to the municipal water and sewer system, a bathroom and sink must be added, the flooring needs to be replaced with vinyl tile and heating issues caused by exhaust from the art room kiln are in need of repair. Back to top 5. What is the projected timeline for this project? If voters approve the $1.398 million capital project on December12, plans would be submitted to the State Education Department for approval the following month. Pending approval, the project could go out to bid in the spring. Work could commence in June and be completed for the 2007-08 school year.