Who initiates a Gateway review?
The responsibility for initiating a Gateway review rests with the Senior Responsible Owner (SRO) of the project. The program or project manager should identify the level of risk of their project and in consultation with their SRO may nominate the program or project for review. Around 8-12 weeks before the review will take place, the SRO and the DTF Gateway Unit will agree on the dates for the review and the skills and experience required for the review team.