When will street/traffic markings (stop bars, cross walk striping, bike lane striping, etc.) be replaced?
Painting of the street markings is one of the last activities of a sewer main replacement project. To insure that there will not be any further excavation in the area this portion of the work is delayed until approximately four weeks after all sewer main replacement construction activities have been completed.