When will my lot be sodded?
In accordance with the subdivision agreement, the developer shall ensure that the builder completes the sodding of each lot shown on the plan no later that 6 months after the date of occupancy of the dwelling unit on that lot. Dwelling units to be occupied between November 1 and June 15 of the following year, shall be complete by June 30th following such occupancy.