Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

When the supplier for a process specified by the drawing is changed, must the FAI be redone?

0
Posted

When the supplier for a process specified by the drawing is changed, must the FAI be redone?

0

B6. Response: Yes, you or your new supplier must perform a partial FAI covering the processes/characteristics moved. Moving to a new supplier provides the “Potential” to affect fit, form or function. Also see answer to question B3. B7. Question: If a baseline FAI exists but is to a system used prior to 9102, must the baseline FAI be updated to 9102 prior to performing a new partial FAI. B7. Response: 9102 is not retroactive. A 9102 partial may be completed using the original completed baseline.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123