Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

When should an Idaho Mechanics Lien Claim be filed?

claim filed Idaho lien mechanics
0
Posted

When should an Idaho Mechanics Lien Claim be filed?

0

The filing of an Idaho construction lien must be completed within ninety days after the completion of the labor or services or furnishing of materials, or the cessation of the labor, services or furnishing of materials for any cause.