Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

When should a North Carolina Mechanics Lien Claim be filed?

0
Posted

When should a North Carolina Mechanics Lien Claim be filed?

0

North Carolina mechanics liens on real property must be filed within 120 days of the last date the lienor provided materials or services to the Project. North Carolina mechanics liens filed by subcontractors and below have different deadlines depending on who is filing the North Carolina construction lien.