Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

When is the HP draw the greatest on a dredging project?

draw dredging HP project
0
Posted

When is the HP draw the greatest on a dredging project?

0

The power required by the pump will increase as the pipeline length increases until the full load (max. horsepower) – full speed (max. pump RPM) point is reached. Beyond that point, the power requirement decreases as the pipeline lengthens. Note: If the flow rate is higher than required to carry the slurry, it will use more HP than needed, wasting fuel. The most efficient dredging is done at the lowest velocity that will carry the maximum slurry density.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123