When is a stormwater management system required to provide attenuation for the 2-year/24-hour storm event?
For systems serving new construction that is greater than 50 percent impervious over the project area, the post-development peak discharge rate must not exceed the pre-development peak discharge rate for the 2-year, 24-hour design storm event. When calculating the impervious area for this purpose, exclude water bodies and the area providing stormwater treatment.