Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

When is a contractor or supplier deemed to have last performed work or furnished materials so as to trigger the start of the lien filing?

0
Posted

When is a contractor or supplier deemed to have last performed work or furnished materials so as to trigger the start of the lien filing?

0

The last day that labor or materials are furnished that are necessary to fulfill the requirements of the contract is deemed as the last day of work, which begins the start of the lien filing period.