When I notify regarding a demolition, do I give the start date of the demolition or of the asbestos removal? Which date do I use to determine whether Ive met the 10-day waiting period?
For asbestos removal, the start date is ten (10) working days from delivery of the notice to the date that the removal or any removal related activity that disturbs the asbestos containing material begins. The date that the demolition is to begin should be reported on a separate notice. The waiting period should be calculated based on the start date of the demolition, or ten (10) working days following the completion of asbestos removal at the site. The waiting period is necessary to give inspectors time to visit the site before any activity begins.
For a demolition, the start date is the date that the removal or any removal related activity begins. The date the demolition starts also must be reported. The waiting period should be calculated based on the start date of the removal or if no removal is required then the start date of the demolition. The waiting period is necessary to give inspectors time to visit the site before activity begins.
For a demolition, the start date is the date that the removal or any removal related activity begins. The date that the demolition starts also must be reported. The waiting period should be calculated based on the start date of the removal or if no removal is required then the start date of the demolition. The waiting period is necessary to give inspectors time to visit the site before activity begins.
For a demolition, the start date is the date that the removal or related activity begins. The date the demolition starts also must be reported. The waiting period should be calculated based on the start date of the removal or the demolition, if no removal is required. The waiting period is necessary to give inspectors time to visit the site before activity begins.