Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

When certifying for progress drawdown reports to the bank on construction progress, what works are recommended for payment?

0
Posted

When certifying for progress drawdown reports to the bank on construction progress, what works are recommended for payment?

0

When certifying for payments, quantity surveyors will only certify on a cost to complete basis, that is all items and trade works that are completed and fixed to site at the date of inspection. Quantity surveyors will not certify for deposits paid on items not fixed to site (unless in exceptional circumstances negotiated between the developer and the bank directly).

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123