What will determine the cost of Reliability Unit Commitment (RUC) under Nodal Market?
Total RUC costs is the sum of Start-up and Minimum Generation costs for RUC committed Resources. The cost will come from Three-Part Offers (TPOs) if committed Resources have valid TPO. Otherwise, the cost will be the verifiable Start-up and Minimum Generation costs or generic cost if there is no approved verifiable cost.