What solutions have you developed to problems that exist along the present route in the Hunter’s Ridge area in Maryland? What are the factors that will dictate final route choice in this area?
A. Dominion is not aware of specific problems in the Hunter’s Ridge area. We acknowledge that this is an area that developed over the years and is fairly congested, but our personnel have satisfactorily operated and maintained the pipeline in this area. The development in this area may influence the final route choice. A key factor is obtaining consent from the Southern Maryland Electric Cooperative for the use of a portion of their easement for construction.