Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

What resource parameters that the QSE submits in the Current Operating Plan (COP) coincide with what is registered?

0
Posted

What resource parameters that the QSE submits in the Current Operating Plan (COP) coincide with what is registered?

0

Registration data in the Resource Asset Registration Form (RARF) will be used within ERCOT systems as initial values. QSEs may change a limited set of parameters for operational purposes. The data submitted within the Current Operating Plan (COP) (by the QSE) will need to be aligned with the naming of the resource and within the reasonability limits (provided by the resource entity in the RARF), for example: high/low reasonability limits.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123