Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

What permits and approvals would GRU need to obtain before building a new generating unit?

0
Posted

What permits and approvals would GRU need to obtain before building a new generating unit?

0

GRU would have to obtain a Site Certification from the Governor and Cabinet using procedures established in Florida’s Electrical Power Plant Siting Act. This is a lengthy process that would require us to obtain a determination of need for additional generating capacity that is in the public’s best interest from the Florida Public Service Commission and demonstrate that the project would meet all of the local, state and federal regulatory requirements applicable to the project. The regulatory agencies and the public would review GRU’s application and participate in hearings before an administrative law judge who would make a recommendation to the Governor and Cabinet, who make the final decision. The Florida Department of Environmental Protection serves as staff to the Governor and Cabinet and coordinates the review process. This process takes a number of years, and is one reason we must start soon in order meet our community’s needs by 2011.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123