Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

What lead times can be expected when ordering a Lost Foam casting?

0
Posted

What lead times can be expected when ordering a Lost Foam casting?

0

As with all processes, lead times vary greatly depending on part complexity. Generally, 8 to 16 weeks is typical for completed tooling and first castings produced. After casting approval, 6 to 12 weeks is typical for production run startup. Rapid prototyping methods can produce castings in as little as 2 to 3 weeks. The information provided in this feature article is of a general nature and is intended to provide initial guidelines for process consideration. As with all processes, each project will face advantages and disadvantages during design and production. If you have more specific questions for a project that you are considering, please contact us using the Request More Information form on our website. We will be happy to discuss your project with you.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123