What is trade-off triangle?
Trade-off triangle is a relationship between the project variables of resources (people and money), schedule (time), and features (scope). These variables exist in a triangular relationship. After you have established the triangle, any change to one of its sides requires a correction on one or both of the other sides to maintain project balance. This includes, potentially, the same side on which the change first occurred.