What is the typical lead time for delivery of a monorail system?
Each system and project requirements are different and will have an impact on specification and design. Curently standard delivery is 20 to 26 weeks from issue of order. TMD and Scharf always do everything possible to meet a clients specific projects needs. Often it is possible because of the scaleable nature of the monorail to take early delivery of a portion of a system. As a project ramps up to full production additional train components are added…