What is the total project period for an award?
The total project period for an award made in response to this FOA may not exceed five years. The grantee is required to begin the design phase immediately upon receipt of the Notice of Award (NOA). Initial schematic designs must be submitted to NCRR no later than four months following the receipt of the NOA. NCRR expects to review those documents in four weeks or less. Design development documentation, incorporating comments from the review of the initial schematic design, must be received within eight months of the release of the NOA. NCRR also expects to review those documents in four weeks or less. The final construction document is due no later than 14 months following the release of the NOA. Following approval of the final construction document, all funds will be released. All funds must be obligated no later than June 30th of the fifth year from the initial date of award.