What is the timetable to install a ViscoRide Track and how long before it is operational?
There is a lead time from the date of the client placing a firm order with deposit to commencement of construction of approximately 6 to 8 weeks. The construction phase for the track surface only is approximately 4 weeks, weather permitting. The track is fully operational on handover to the client. Should major earthworks and construction be required, ViscoRide would give a detailed time frame on expression of interest.