What is the time period to commence building?
There is no build by date. Once a site is handed over for construction the owner has 15 months from that date to complete the construction, which is defined as the issue of a practical completion certificate. If the house is not completed within 15 months a penalty of R10 000.00 per month is payable until the house is completed.