What is the time frame for poured projects and decorative concrete?
A 3-day timetable on a poured foundation wall project, after excavation is complete, is fairly typical. Decorative concrete is a bit more labor and time intensive;about 7 days from starting to completion. First the forms are set and the base is poured. We then pattern the base color of concrete if it hasn’t been pre-colored throughout the mix. We add any special coloring effects. After allowing the coloration to dry a bit, we do final touch-ups and final sealing. Factors like weather and the size of the project can affect the schedule.