What is the Tender Evaluation process for EVM?
The EVM requirement lies within the Project Management aspects of the Tender so the Tender Evaluation Working Group (TEWG) assigned to evaluate the EVM part of a tenderer’s response will logically reside with the Project Management TEWG. The EVM component will include a detailed review of the draft EVM plan and a cursory review of the CWBS and CMS. These areas are normally reviewed in detail by other areas of the project office but, due to their importance in EVM, it is necessary to review these draft documents to ensure that the basis for the EVM system will be adequate. There are other areas that will be reviewed including but not limited to the draft contract for the access clauses, subcontractor flow down, and other measurement aspects.