What is the schedule for the construction of the Sigma plant?
Five years are needed to plan, build and commission a plant for industrial-scale production (270 million litres of synthetic biofuel per year). The design will of course draw on experience from the Beta plant at Freiberg. Provided the final decision on investment is made in 2010, production could begin in 2013/2014.