What is the schedule for construction of the NEON infrastructure?
Constructing the entire NEON network will take approximately five years. The first year and a half or so will be devoted to constructing site facilities in two domains within which NEON, Inc. has the longest standing relationships. Thereafter, NEON, Inc. will construct site facilities in six domains per year over the next three years. The order of domain construction will depend primarily on project management considerations such as weather and the ability to obtain permits. Currently, NEON, Inc. envisions building all facilities within a given domain at the same time unless project management considerations lead to a more effective option.