Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

What is the requirement on clean-outs and slope of the building sewer?

0
Posted

What is the requirement on clean-outs and slope of the building sewer?

0

A clean-out should be located for each 75 foot length of the sewer line and also at any changes in grades or alignments greater than 45 degrees. The slope of the building sewer should be 1/8 inch per foot minimum.