Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

What is the proposed in-service date for the offshore wind project?

0
Posted

What is the proposed in-service date for the offshore wind project?

0

In April 2009, an application was filed to interconnect the offshore wind project with the New York Independent System Operator (NYISO), operators of the state’s power grid, for up to 700 MW by 2015.

0
10

In April 2009, an application was filed to interconnect the offshore wind project with the NYISO for up to 700 MW with an anticipated operational date of 2015. However, current projections of the permitting process would estimate the project’s commercial operation date no earlier than 2016 or 2017.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123