What is the process for obtaining a Land Disturbance Permit?
Submit five sets of complete site plans, two copies of the hydrological report, and a copy of the certificate from Cobb County for the completion of its approved erosion and sedimentation control course. The review fee is due at the time you submit your plans. Please contact (770) 944-4325 to determine your review fee. Comments are generated within two weeks. Once site plans are approved a Land Disturbance permit may be issued. Generally, the processing time for a permit is 45 days.