What is the process for hydrostatic testing?
A. Water is withdrawn from the predetermined water source through a screened intake hose, per any applicable state permits. Once the pipe segment to be tested is full of water, the pressure is pumped up to the required test pressure. The test is held for the required time, usually eight hours. After the pressure is relieved, the water is discharged through the erosion control structures required in the permits.