Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

What is the period of construction for a new allotted Industrial Plot?

0
Posted

What is the period of construction for a new allotted Industrial Plot?

0

As per order issued on 9.1.98, construction of building is to be allowed within seven Years after realisation of composition charges having three years as grace period. Two more years have also been allowed for construction from the date of issue of execution of lease deed whichever is later. Return to TOP..