Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

What is the normal building cycle for 2000 square feet or less?

building CYCLE feet normal square
0
Posted

What is the normal building cycle for 2000 square feet or less?

0

• Day 1 – Dig • Day 2 – Skip • Day 3 – Dig & pour footings • Day 4 – Set and pour walls • Day 5 – Strip forms from walls • Day 6 – Waterproof • a. Builder to have a plumber • b. Builder to have termite treatment • Day 7 – Exterior draintile • Day 8 – Backfill inspection • Day 9 – Backfill • Day 10 – Prep basement/garage slab • Day 11 – Basement slab inspection • Day 12 – Pour basement/garage slab • Q: How do I get on the schedule? A: Modern Foundations typically schedules 2-4 weeks in advance. This time frame begins with the signing of a contract and may change due to work load and weather changes. When we receive a complete signed contract, you will be placed on the schedule. The office will notify you about your approximate scheduled date. • Q: What are the payment terms for Modern Foundations? A: Payment is due within fifteen (15) days from the invoice date. Interest will be charged thirty (30) days from the invoice date. Modern Foundations will accept cash, checks, VISA, MasterCard

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123