What is the “No-Build” alternative?
A. The No-Build alternative is to take no action other than what is already scheduled. VDOT produces a Six-Year Program listing projects it will implement for the next six years. If the No-Build alternative is selected, projects listed in the VDOT’s Six Year Program would be implemented. Also, in metropolitan areas, the No-Build alternative assumes implementation of other committed projects included the Metropolitan Planning Organization’s (MPOs) long-range plan.