What is the LSST schedule and cost?
The LSST is scheduled for first engineering light in 2014 and for early science operations beginning in 2015. Full science operations will begin in 2016. [Calendar years] The LSST project will cost $390M through first light, including all construction, hardware, software, data management, and a 30% contingency. [2006 $] This work-based cost estimate has remained constant within 15% since the beginning of the project phase in 2003. Significant milestones have already been reached, including the casting of the primary/tertiary mirror. The LSST survey will last for ten years.