What is the FERC process?
There are three ways in which the Federal Energy Regulatory Commission could approve this project. One is through the standard multi-stage process that usually takes at least three years; another is through the Alternative Licensing Procedure, which includes everything (studies, public input, etc.) in the regular process but telescopes the timeline involved; a third is through the obtaining of waivers for certain aspects of the process.