What is the extent of the pile coating?
Limits of clean and paint of piles are described in addendum #1. Is it your intention to apply the second coat after driving? This is highly unusual and very expensive. At the option of the Contractor, the final coat of waterborne inorganic zinc coating may be applied at the shop. Please see addendum #1. 50. Section 10-1.33, (page #127) requires a 28 working day set period for the test pile to set prior to static load testing. Does the 28 working days start after the initial driving or after the last retap? A 28 day set period begins after the pile is driven to the specified tip elevation. Please see addendum #1. 51. Where are the control areas for the pile load testing? The control locations for Test Site Location A is from Sta 30+31 to Sta 68+60 and Test Site Location B is from Sta 68+61 to Sta 109+00. Please see addendum #1. 52. Ref: Drawing Sheets 280, 281 and 282. The elevation views of the pile on these drawings show the pile cutoff line referenced to two locations relative to th