Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

What is the escalation process if network problems are experienced that next day after the cutover?

0
Posted

What is the escalation process if network problems are experienced that next day after the cutover?

0

A 10gen project engineer will be onsite the morning after the cutover between 8am-10pm to monitor and help resolve any network issues if they arise. An on-call support number will be setup for the deployment that will divert to the on call support person.