What is the Economic Study Project Timeline?
Aug-Oct, 2006 — Project RFP development, drafting and review: Sept 2006 — 3rd-party review of RFP Nov 2006 — RFP on the street open for bid proposals Dec-Jan, 2007 — RFP proposals evaluation Feb 7, 2007 — Notice of Intent to Award issued Feb, 2007 — Contract development Mar-May, 2007 — Research Plan Development May-Jun, 2007 — Questionnaire Development July 2007 – Feb 2008 — Data Collection Mar-Jul, 2008 — Data Analysis/Economic Model Development Aug- Sept, 2008 — Draft Report(s) Dec, 2008 — Final Report(s)