What is the disposition (availability for continued use) of the two current LSC systems (Xeon and EM64T)at FSL at the beginning of the contract and 10/1/06?
At the beginning of the contract the Xeon system will be maintained on a limited basis, the EM64T system will be fully maintained (subject to final negotiations with the incumbent). As of 9/10/06, there are no concrete plans regarding maintenance, however the Government does not plan to offer any additional GFE.