What is the deadline for submission of a site plan? What is typical timeframe for review?
Site plans submitted prior to noon each Tuesday are typically scheduled for placement on a City Commission agenda three to four weeks later. Multiple copies of a site plan are submitted to the Planning Office. These are distributed to various in-house departments and public utility agencies for review and comment. The Planning Office coordinates the review and prepares a report to the City Commission with recommendations for action. A building permit may not be issued [by the Development Services Division] for a new development until a site plan has been approved and all conditions of approval have been met.