What is the current timeline for new construction and renovation?
The Housing Master Plan provides a three-phased timeline over the next 10 years. The projected timeline for each phase is: • Phase I • Design Phase I/ Bidding ……..Jul. 2011-Jul. 2012 • Construction Housing 1 ……..Jun. 2012-Sep. 2013 • Construction Housing 2 ……..Jun. 2012-Sep. 2013 • Demolition Phase I …………..Dec. 2012-Feb. 2014 • Phase II • Design Phase II/Bidding ………May 2013-May 2014 • Construction Housing 3 ………May 2014-May 2015 • Demolition Phase II …………..Feb. 2015-Jan. 2016 • Phase III • Design Phase III/Bidding ………Jun. 2015-Jul. 2016 • Construction Housing 4 ………..May 2016-Sep 2017 • Demolition Phase III ……………May 2016-Jan 2017 • New Recreation Fields …………May 2017-Aug.