What is the anticipated cost for constructing the Wakarusa Water Reclamation Facility?
The 2003 Wastewater Master Plan estimated the total project cost to be approximately $75 million, which includes acquisition of the plant site property, design, and construction costs. The project also includes $10 million for collection system improvements integral to the WRF, for a total project cost of $85M. The 2004 Rate Study included this capital outlay, which is reflected in the City’s current wastewater rates which will allow the City to continue to provide quality service, maintain the existing infrastructure, and construct capital improvement projects to accommodate system expansion.
Related Questions
- The Wakarusa Water Reclamation Facility will generate sludge or biosolids as a byproduct of the treatment process. How will that material be disposed of?
- Has the pipeline route that will convey sewage to the new Wakarusa Water Reclamation Facility been determined?
- What is the anticipated cost for constructing the Wakarusa Water Reclamation Facility?